Delivered on time and on budget through a combination of CCG Manufacturing and CCG Asset Management, the last programme delivered for the association saw over 320 PVCu windows installed across 47 Partick residences.
Delivered fully on a supply-and-fit basis through Scotland Excel, the steel-reinforced, A-energy-rated windows were specified to complement the rich architectural diversity seen throughout the area, with some windows reaching 2.7m in height, designed accordingly following pre-contract building and weather analysis performed by CCG’s PVCu partner and polymer supplier, REHAU.
The contract was successfully delivered within a remarkable nine-week programme, despite the exceptionally low temperatures experienced during the winter months. Its success led to the award of further workstreams, which commenced in late summer 2026, and resides alongside recent new-build developments such as Bearsden Road, completed in 2025
Client:
Partick Housing Association