Procured through the Scottish Procurement Alliance, and following a comprehensive survey and tenant engagement initiative, CCG began work in 2022, commencing with Kyle Court in Cambuslang – a multi-storey residence located just two miles from the point at which CCG’s engineered timber fire door sets are manufactured.
Kyle Court was the first of ten high-rise flatted blocks – 1700 properties – in Cambuslang, Rutherglen, East Kilbride and Hamilton to receive a mix of FD60-rated main entrance, flat entrance, common passage, and common door sets, with over 4000 installed over a 3.5-year programme.
Every door set that was installed is fully BM Trada Q-Mark and Secured by Design accredited and fabricated in CCG’s advanced Timber Manufacturing hub in Cambuslang, before being installed by CCG Asset Management.
The £10m workstream was completed on behalf of the council in summer 2026.
Client:
South Lanarkshire Council